Quick answer
An Unsatisfactory EICR means C1 or C2 codes were found. C1 requires immediate action; C2 must be fixed within 28 days. C3 is a recommendation only. We quote remedials clearly and include a free retest.
Satisfactory vs unsatisfactory — what it means
An EICR ends with one of two overall outcomes: Satisfactory or Unsatisfactory.
A Satisfactory report means no C1 or C2 codes were found. The installation is considered safe to continue in service. You can let the property and provide the certificate to tenants as normal.
An Unsatisfactory report means at least one C1 or C2 code was identified. You must arrange remedial work — you cannot simply ignore the report and continue letting without addressing the issues.
C1, C2, C3 and FI codes explained
Every observation on an EICR is coded. Here is what each means for landlords:
- C1 — Danger present. Immediate risk to safety. Examples: exposed live conductors, severely damaged consumer unit, missing earthing. Work must be made safe immediately — often on the day of inspection.
- C2 — Potentially dangerous. Urgent remedial work required within 28 days. Examples: no RCD protection on circuits, outdated consumer unit, loose connections, missing bonding.
- C3 — Improvement recommended. Not immediately dangerous but does not meet current standards. Examples: old fuse box still functional, missing surge protection. Not legally mandatory to fix, but good practice.
- FI — Further investigation required. The inspector could not fully test a circuit and needs to return. Treat as urgent until resolved.
The 28-day deadline for C1 and C2
Under the 2020 Regulations, you must ensure remedial work for any C1 or C2 code is completed within 28 days of the inspection (or sooner for C1 where immediate danger exists).
After remedial work, the installation should be retested to confirm the codes are cleared. We include a free retest on all remedial work we carry out — so your updated Satisfactory certificate is issued without an additional inspection fee.
Keep records of all remedial work and the updated certificate. Councils and letting agents may request evidence of compliance.
Can you still let the property?
With C2 codes outstanding beyond 28 days, you are in breach of the regulations. C1 must be made safe immediately; written confirmation of completed remedial work is due within 28 days. That is not an automatic statutory occupancy ban or eviction.
In practice, many landlords receive an Unsatisfactory report, book remedial work promptly, and continue letting once work is complete and the retest confirms Satisfactory. The key is acting within the 28-day window — not ignoring the report.
Common failures on Manchester rental stock include consumer units without RCD protection, missing main bonding, and outdated wiring in Victorian terraces across Chorlton, Didsbury, and Salford.
Get a remedial quote
We quote all remedial work clearly before starting — no surprise invoices. Most consumer unit upgrades in Greater Manchester are completed within 1–2 weeks of the initial EICR.
Request a remedial quote → or read our full landlord EICR services →
Fixed EICR prices across Greater Manchester
1–2 bed £169 · 3 bed £199 · 4 bed £239 · HMO £55/room (min £275). No call-out fee. Same-day certificate.
Common questions on this topic
Still have questions? Book online or get in touch
We respond to enquiries within one working day